Sunday, November 24, 2024
Home > Featured > High Court Blocks FINASI From Evicting Roko Construction From Lubowa Specialised Hospital Construction Site
FeaturedNews

High Court Blocks FINASI From Evicting Roko Construction From Lubowa Specialised Hospital Construction Site

The High Court in Kampala on Thursday placed an injunction on two construction companies, blocking them from evicting Roko Construction company from the construction site of the Lubowa Specialised Hospital.

According to court ruling delivered by Justice Andrew K Bashaija of the High Court Civil Division, construction companies FINASI/ROKO CONSTRUCTION SPV LTD and FINASI INTERNATIONAL FZC have been blocked from evicting ROKO Construction from the site.

“A temporary injunction doth issue to restrain the 1st and 2nd Respondents, their officials, agents, or anyone acting under their authority, orders or instructions from evicting the Applicant from the site for the International Specialized Hospital in Uganda at Lubowa, Wakiso District, until the petition filed by the Applicant against the 1st and 2nd Respondents is heard and disposed of,” the ruling reads in part.

It adds, “A temporary injunction cloth issue to restrain the 1st and 2nd Respondents (FINASI/ROKO CONSTRUCTION SPV LTD and FINASI INTERNATIONAL FZC), their officials, agents, or anyone acting under their orders, directions or control from interfering with the Applicant’s execution of the contract works and possession of the site for the International Specialized Hospital in Uganda at Lubowa, Wakiso District until the petition filed by the Applicant against the 1 st and 2nd Respondents is heard and disposed of.”

Early last month, drama ensued at the construction site for the much publicized Lubowa International Hospital as security tried to evict the contractor, Roko Construction Company Ltd.

The standoff which involved Roko Construction boss, Mark Koehler, started when Enrica Pinnetti, the boss of FINASI tried to evict the construction company from the site and replace it with China Power, a construction firm based in China.

Roko is the government approved contractor for the project while FINASI is the equipment supplier.

In March this year, Parliament approved a guarantee of USD 379 million (1.4 trillion Shillings) for the construction of an International Specialized Hospital in Lubowa, Wakiso district.

The facility with a 264-bed specialized Healthcare capacity will be operated as a world-class internationally accredited facility to treat conditions for which Ugandans have been travelling abroad. The conditions include cancer treatment, heart diseases, organ transplant, fertility treatment, highly specialized surgeries, and bone marrow transplant, among others.

The government sought authorization of parliament for the project following a proposal by the Italian investors Finasi Roko Construction SPV Limited, a major member of the FINASI-RoKo consortium, an entity which specializes in the construction of turnkey health care facilities.

The investor wanted to have the project financed through a promissory note from the Ugandan government as a public-private partnership. Under the arrangement, the government will finance the firm to construct and run the specialized facility and payback within eight years from the commencement of operations.

But the request was queried by Members of Parliament who questioned why the government had to invite an investor, who has to be guaranteed with huge sums of money. They also objected to the high-interest rate of 477 billion Shillings and the purpose of financing the facility, considering the poorly financed hospitals across the country.
However, the request was endorsed by the National Economy Committee of Parliament which had been given a task to review the application and interact with key players in the health and finance sectors to establish whether the partnership has value for money.

Members also rejected a minority report which had been presented by Mukono Municipality MP Betty Nambooze, to block the funding. In support of the Minority report, Butambala County MP Muwanga Kivumbi said that the cost of constructing the hospital is exaggerated.

Bunyole West MP James Waluswaka says the proposal is risky. He faulted the government for picking on an investor without undertaking a bidding process to guarantee that anyone who gets the promissory note is selected on merit.

Dokolo Woman MP Cecilia Ogwal says that the specialized women hospital was built at only about USD 25 million (92 billion Shillings) far less than the USD 379 million (1.4 trillion Shillings) that is needed by the investors to construct the International Specialized Hospital. She says there is a possibility that all parts of the proposal constitute illegality.

Despite the doubts, Parliament sanctioned the proposal. The speaker of Parliament Rebecca Kadaga observed that the project is of immense benefit to Ugandans.

According to the breakdown of the money, the purchase, delivery and installation of medical equipment, hospital furniture, testing, commissioning and training will cost 370 billion Shillings, civil works excluding mobilization costs will cost 320 billion Shillings, medicines and consumables for a year are budgeted at 62 billion Shillings and preliminary project development is 50 billion Shillings.

Government is expected to take over the hospital after ten years according to the agreement

Leave a Reply

Your email address will not be published. Required fields are marked *