Gov’t Dismisses Reports Of Cracks On New Bridge

The Uganda government has dismissed social media reports that the famous Source of the Nile Bridge has developed cracks.

In a statement issued on Sunday, government says the reports are misplaced explaining that the contractor is in the process of applying permanent asphalt.

Below is the full statement

January 27th 2019.

In an earlier communication, the Uganda National Roads Authority [UNRA] informed the public that the Contractor on the Source of the Nile Bridge in Jinja was conducting several tests to form a base line data for the Bridge Structural Health monitoring.

We also added that the wearing course seen and referred to as ‘bumpy’ or cracked by a section of the public is a non structural attachment and therefore not a defect on the bridge.

It’s to be replaced with permanent asphalt as soon as investigation on structural behaviour is concluded and baseline data is formed. This will be done within the defect liability period before contractor leaves the site.

At the moment, the Contractor has completed all the tests and has embarked on plans to start application of permanent asphalt on the bridge deck but as a contractual requirement they are preparing a trial section of asphalt on the bridge at the length of approximately 100m on both approaches of the bridge.

This is ongoing and the exercise shall not interrupt the flow of traffic on the bridge.

#GoUworks